Chapter
8
MANAGING
/ MONITORING THE CONTRACT
Once
you have a signed contract and the service provider has begun work, it is
important to monitor the service provider’s performance under the contract and
to promptly deal with any problems that arise. This is often referred to as
contract management. Monitoring performance under the contract is also required
by the Accountable Government Act. See Iowa Code section 8.47. Chapter
10 contains information about the types of monitoring clauses described in the
administrative rules that implement the Accountable Government Act as it
relates to services contracting.
8.1 MONITORING CONTRACT PERFORMANCE
Monitoring
means any planned, ongoing, or periodic activity that measures and ensures
contractor compliance with the terms, conditions, and requirements of a
contract. The annotated Model Contract in Appendix I includes
an example of a set of contract clauses that may be used to spell out contract
management procedures in the contract itself.
• • The purpose of
monitoring is to assist the contractor in
– − Complying
with the terms and conditions of the contract and applicable laws and
regulations.
− – Preventing
non-compliance by identifying and resolving potential problems by providing
constructive, timely feedback.
– − Making
progress toward the expected results and outcomes.
While
the contractor has responsibility to perform under the terms of the contract,
the state agency has responsibility for reasonable and necessary monitoring of
the contractor’s performance. Effective contract monitoring can assist in
identifying and reducing fiscal or program risks as early as possible, thus
protecting public funds.
Monitoring
may be viewed as:
− – A preventative
function.
– −
An opportunity to determine the need for technical assistance.
– −
A valuable source of information concerning the effectiveness of services and
service delivery methods.
You should plan on identifying an individual
in your agency to serve as the contract manager. Although the contract manager
may delegate certain functions, the contract manager provides the principal
contract management and monitoring function and is the person responsible for
ensuring that the management and monitoring functions are done and done well.
The contract manager provides the principal contract management and monitoring
function. The chief objective of the contract manager is to ensure that the
contractor fulfills all contractual obligations in a quality manner within
schedule and within budget. To accomplish this task, the contract manager must
be completely knowledgeable of the terms of the contract and maintain requisite
controls throughout.
To
effectively manage the contract, the contract manager should establish controls
and monitor performance to ensure all work is completed within the requirements
of the contract. To get good results from a contractor, precise performance
objectives must be set. The contractor needs to know exactly what is expected
and when it is expected. The mechanism for monitoring the contract should be
set out in the contract. Appendix J contains a possible format and example of a
tool that you might be able to use for monitoring a contract.
By
assuming a dynamic role in contract administration, the contract manager is more
likely to discover and resolve problems in the early stages of the contract and
avoid "crisis management" later. If there is a lack of quality or
performance at any milestone point, this needs to be communicated to the
contractor without delay and the appropriate changes or corrections made. This
lends a posture of competent management throughout the project and provides the
leadership required for successful contract completion.
• • Monitoring
Plan
One
means of defining the specific monitoring methods appropriate to the particular
service and the monitoring activities to be completed for an individual
contractor is a monitoring plan. The plan can identify the tools to measure and
assess contract performance and compliance, and the process for collecting
information. Monitoring plans can also be used to decide which contracts to
monitor, based on risk, and can also enable an agency to assess the contract
management resources necessary to ensure adequate oversight. The level of
monitoring should be commensurate with the importance or sensitivity of the
service. Further, the plan can identify how monitoring activities might be
coordinated between multiple state agencies providing funding to a contractor.
• • Monitoring
activities may include:
− – Periodic
contractor reporting: Require the contractor to submit progress reports or
other appropriate data or reports, based on pre–defined criteria, and review
the contractor’s reports for verification of services provided and adherence to
the contract. Substandard performance should be identified and addressed timely
and appropriately.
− – Invoice
reviews: Compare billings with the terms agreed upon in the contract.
Ensure the costs or payments being charged are within the contract parameters.
− – Other
periodic contact with contractor: On site visits to maintain contact with
the contractor to review progress on a regular basis. Good contract
monitoring includes a continuous dialogue with the contractor.
− – Accountable
Government Act Provisions: Monitoring activities may also include the types
of monitoring plans described in the contract in accordance with the
Accountable Government Act and the rules implementing it. Chapter 10 provides
additional information about the types of monitoring plans described in the
rules.
Every
communication with a contractor is an opportunity to monitor activity. Adequate
documentation is essential for effective contract monitoring. Contract files
should include copies of letters, meeting notes, and documentation of phone
conversations as evidence that conscientious monitoring has occurred during the
period of the contract.
Fiscal
monitoring includes a review of the contractor’s invoices and supporting
documentation. Before authorizing payment, contract managers should ensure the
contractor has adequately demonstrated the satisfactory delivery of services as
agreed to in the contract. Contract managers should verify the accuracy of the
contractor’s invoices and documentation, whether billings are consistent with
contract requirements, and whether total payments are within the limits set by
the contract. Contract managers should ensure that payment documentation is on
file.
8.2
MANAGING PAPER
In
addition to monitoring contract performance, you must also make sure that the
service provider has provided all of the “paper” required by the contract. For
example, if your contract requires the service provider to provide the agency
with a certificate of its insurance coverage, you need to make sure that you
get the certificate and that it includes the coverage that it is supposed to
include. A copy should be kept in your contract file. If your contract requires
the service provider to provide the agency with other items (such as evidence
that it holds an active license or any necessary certifications), you should
make sure that you have received those things as well.
8.3
MANAGING INFORMATION TECHNOLOGY (IT) CONTRACTS
A
clear and concise Statement of Work with detailed design and operational
specifications and standards, tasks, resources, deliverables, work plan,
milestones, etc. managed by a project manager/team is an effective tool for
managing an IT (or any other) contract. If necessary provide project management
training to the internal staff assigned to the project, or hire consultants
with project management, Quality Assurance (QA) and Independent Verification
and Validation (IV&V) skills as necessary.
Developing
a clear and concise statement of work is the challenge. The better the quality
and precision of the statements of work, the more opportunity to monitor the
work, control costs, monitor time, reduce and/or eliminate scope creep, review
deliverables and improve your chance of success. The more ambiguous, the
greater the potential for problems to occur, loss of control, overruns and
failure.
In
addition to design and operational specifications (mandatory requirements),
statements of work should also include a project work plan, performance
expectations, and payment milestones. A manageable change control procedure is
a must as it is unlikely that you will be able to predetermine and include all
of the issues, aspects, and changes and conditions that may arise prior to
final acceptance and completion of the project (the longer the performance
period the more changes that are likely).
Establish
a review and acceptance testing procedure, document results of acceptance
testing, and send notices and reports to the vendor identifying any and all
deficiencies that need to be corrected. It is a good practice to include
language in the contract that permits you to withhold or retain all or a
portion of payments to be made to the vendor until deliverables have been
satisfactorily provided and the system meets all specifications, performance
standards and has passed acceptance testing. A warranty period (e.g., one-year
warranty) should commence following the State’s acceptance of the entire
project or system.
8.4
REVIEWING INVOICES FOR PAYMENT
Contract
payment is the process by which the contractor submits invoices for
reimbursement of service and receives payment. The contract manager, who is
responsible for evaluating performance of the contract, must carefully audit
the contractor’s requests for payment to verify the accuracy of all charges.
The contract manager should determine if the number of hours
or costs or payments are commensurate with the services or deliverables
received. The contract manager must also verify that rates for the contractor
or subcontractor(s) are as stated in the contract. All documentation submitted
must be verified to assure that all charges for the services are justified.
Travel
expenses must also be verified to be consistent with contract terms. Most state
contracts which require reimbursement shall not exceed the limits established
for board and commission members in the Department of Revenue and Finance’s
Procedure 240.102VI. The reasonableness of personal vehicle mileage should be
checked if allowable under the contract terms. Other types of expenses charged
should be verified to determine if they are allowable under the contract and,
if so, whether they are appropriate. Receipts should be attached for travel
expenses, if required in the contract terms.
The
contract manager must be conscientious to prevent any overpayment to the
contractor. Contract overpayment is any payment in excess of the amount agreed
upon for work performed or in violation of the terms of the contract. The
contract manager must verify receipt of services in accordance with the contract
prior to authorizing payment of invoices. If the services received are not
acceptable or not in accordance with the contract terms, the contract manager
should authorize payment only for those services received that are in
accordance with the contract terms and conditions. The contract manager may
withhold payment for all other charges until the contract terms and conditions
have been met.
8.5
CORRECTIVE ACTION
Corrective
action means action taken by the contractor that corrects identified
deficiencies, produces recommended improvements, or demonstrates that
deficiencies or findings are either invalid or do not warrant action.
Corrective
action is suggested when identified deficiencies are serious (for example, a
failure to complete key deliverables by dates mandated by the Legislature) or
where less formal means have failed. Contract problems should be addressed
immediately, before they become recurring or serious. Contract managers should
check to see if their agency or administrative unit has guidelines or
directives for taking corrective action. If so, follow those guidelines or
directives.
Serious
contract problems that warrant corrective action include:
– Failure to
produce or submit key deliverables
– Significant
audit or monitoring findings
– Inferior
quality of services
– Failure to
perform all or part of the contract
– Late
performance
– Late
submission of reports on a recurring basis
For
the staff completing corrective action with contractors, typical
responsibilities include:
– Communicating
contract remedies, as appropriate, when the contractor’s performance is
deficient.
– Seeking
specialist advice, including legal counsel, when unsure of the rights of either
party or the correct action.
To
address minor problems or first occurrences of problems, contract managers
should:
– Notify the
contractor both verbally and in writing that a problem has been identified.
– Notify the
contractor of expectations for correcting the problem or, if appropriate, ask
the contractor to advise how the problem will be corrected.
– Specify a
date or time when you expect the problem to be resolved or action taken.
– Document
conversations with the contractor by a memo to the contract file, and/or follow
up with a written letter to the contractor.
To
address recurring or serious contract problems, contract managers should:
– Document
conversations with the contractor and set time frames for corrective action.
– Check
to see if applicable law or regulations direct how corrective action must
occur. If so, comply with the legal requirements.
– Clearly
identify the problem verbally and in writing. Be specific by using dates,
number of occurrences, or other data that quantifies the problem. For example,
“Paragraph 4 of your Contract states that you must submit a report by the 5th
of each month. Your reports for May, June, and July were all submitted over 5
weeks after the due date, and we have not yet received your August report.”
– Advise
the contractor in writing about the requirements to correct the problem or, if
appropriate, ask the contractor to submit a corrective action plan, including
dates when corrective action will be completed. Set a deadline for submission
of the plan. If this results in any changes to the contract, amend the
contract.
– Specify a date or time
frame for resolution. Unless a shorter or longer time frame is warranted,
expect corrective action to be completed within one month.
– Track all corrective
action to ensure completion.
– If a deadline is missed
or corrective action is otherwise not completed, follow up in writing
immediately. Notify the contractor that a deadline has been missed and ask the
contractor when the action will be completed. Advise the contractor that
failure to comply with the corrective action plan could lead to termination of
the contract. Note: Failure by contract managers to follow up on corrective
action could be interpreted later by the court as a waiver.
– If the corrective
action is successful in resolving problems, notify the contractor in writing
that resolution has been achieved. Remember to document this in the contract
file.
8.6 WHEN A CONTRACT GOES BAD
Some contracts contain a provision for resolution of
disputes. A dispute involves a difference of opinion between the agency and
contractor about contract terms or expectations. When a dispute occurs, you
should consult with your assistant attorney general about your options. You
should be prepared to provide your assistant attorney general with copies of
the contract, your contract management documentation, and you will also
probably need to be prepared to answer questions the assistant attorney general
has. You should also be prepared to track down additional information that the
assistant attorney general asks for.
8.7 CONTRACT TERMINATION Contracts
may be terminated prior to the completion date of the contract as provided
under the contract terms.
• • Termination Upon Notice
The
termination upon notice clause is intended to handle changed conditions under
the contract, particularly when the expectations of the parties have been
subjected to substantial change.
• • Termination for Lack of Funding
The termination for lack
of funding or nonappropriation is intended to provide
an agency with the opportunity to get out of a contract if the legislature does
not appropriate enough money to the agency to continue the contract or if a deappropriation leaves the agency with insufficient
resources to continue the contract.
• • Immediate Termination
There are some situations
when an agency will need to be able to terminate a contract immediately. For
example, if an agency has a contract with a service provider that must be
licensed to legally provide the contracted services and the service provider
loses its license, the agency needs to be able to immediately terminate the
contract. The contract needs to have a clause that allows the agency to
terminate the contract immediately.
• • Termination for Cause
To
terminate a contract based upon the other party's default, the party asserting
default must demonstrate that there has been a material breach in one or more
of the terms or conditions of the contract. By invoking the termination for
default clause, the agency is generally in a position to claim damages due to
the other party's breach of the contract. Writing clear and specific contract
language will help avoid this type of action.
The
Attorney General's Office should always be contacted when an agency is
considering terminating a contract.
8.8
AUDIT Auditing is defined as a
systematic process of objectively obtaining and evaluating documentation to
ascertain the fairness of management’s representation of financial statements,
internal controls, and compliance with applicable laws and regulations. Audits
may be required by law, as is the case for federally funded contracts (refer to
OMB Circular A-133, Audits of States, Local Governments, and Non-Profit
Organizations at www.whitehouse.gov/OMB/circulars
). When writing contracts, agencies should consider whether an A-133 audit is required
and whether that meets the audit needs. If not, the agency may require an audit
beyond those required by law. When law does not require an audit, state
agencies should use a risk-assessment process to consider whether an audit of
the contractor is needed. When an audit is deemed appropriate and necessary,
the expectations for the audit scope, methodology and due date should be
included in the written contract.
An
audit can be designed to accomplish one or more of the following:
− − Provide reasonable
assurance as to the financial information reported by or obtained from the
contractor.
− − Assess the financial
condition of a contractor.
− − Assess the internal
control system of a contractor.
− − Assess the performance
of a contractor.
− − Assess
compliance with applicable laws and contract regulations.
While an audit can be an effective monitoring tool,
it carries a cost. Therefore, it is incumbent that care be exercised in calling
for audits.
Handling Questioned Costs or Payments
Questioned costs or payments are normally those costs
or payments associated with an audit finding. These costs or payments can be
handled in several ways. First, a decision on whether or not to pursue recovery
of the questioned costs or payments should be made. There may be good reasons
not to pursue recovery of the questioned costs or payments.
Options for recovering questioned costs or payments
may include:
− − Billing the contractor
− − Adjusting future
payments until the questioned costs or payments have been recovered
− − Deducting the
questioned costs or payments from the final payment
You may want to consult with your assistant attorney
general about handling questioned costs or payments.
Contracts dealing with federal funds may require
different processes. Also, it is important to note that when recovering
questioned costs or payments, the repayment by the contractor is generally not
an allowable cost for current contracts.
8.9 REVIEW AND IMPLEMENT CONTRACTOR’S FINAL PRODUCT
Once the contract has ended, contract managers are
responsible for:
− − Following up on any
activities that the contractor is completing (i.e., final report).
− − Ensuring all invoices
are received and paid, and making final payments to the contractor.
− − Assessing whether objectives
and outcomes have been met.
When contract work is completed, the contractor may
be required to submit a final report. Not all contracts will require such a
report, but when they do, the final written product should address, at a
minimum, the following areas as appropriate to the type of consulting service
provided:
− − Statement
of the problem investigated or need addressed.
− − Description
of the methodology used.
− − Alternative
solutions or approaches available.
− − Selected
solution or approach and reasons for selection.
− − Benefits
or results to be realized.
− − Recommendations
for further improvements.
− − Other
matters which should receive management emphasis or attention.
Once results have been accepted, an agency is
responsible for correcting identified problems and implementing the
recommendations. Follow-through by agency management on work done by the
contractor is critical to the success of the overall project. The final report
should be thoroughly reviewed with the contractor to ensure that all
conclusions, supporting logic and related information are understood by the
agency.
When the contractor's final report is accepted by an
agency, the contract manager, or other responsible agency personnel, should
develop a monitoring plan detailing the steps necessary to implement the
recommendations.
The work plan should take into consideration the
following factors:
− − Which recommendations
are to be implemented?
− − What agency resources
are required to proceed with implementation?
− − Is staff sufficiently
trained or prepared to proceed with any changes required?
− − What tasks are required
to implement each recommendation?
− − Whose responsibility is
it to complete each task?
− − How and when will
implementation be accomplished?
Appendix I: http://das.gse.iowa.gov/procurement/AppI_ModelContract.html
Appendix J: http://das.gse.iowa.gov/procurement/AppJ_MonitoringTool.html